Jomax Construction 6” wireline – Greenley, CO

2018-02-14T11:11:27+00:00

Client: Jomax Construction

Time-line: 4 days

Equipment Used: 100 JT Ditch Witch directional drill

Distance: 950’

Location: Greenley, CO

Client Issue: Client needed to place a gas pipeline unde a large construction project.

Americom Solution: Americom used it’s large 100 JT directional drill to meet the timeline, budget and expecation.

Breckenridge Ski Resort – Breckenridge, CO

2017-11-08T11:11:14+00:00

Scope of work: Performed a 950’ / 10” storm drain bore for large building construction site on budget and on time.

Client: PCL Construction Services, Inc.

Time-line: 4 days

Equipment Used: JT100 Ditch Witch directional drill

Distance: 950’

Location: Breckenridge, CO

Client Issue: Client needed a clean water separation for new building for water run off.

Americom Solution: Americom used it’s large JT100 directional drill to drill in on grade 10” […]

Leap Year sewer project – Breckenridge, CO

2017-11-08T10:47:45+00:00

Scope of work: Performed a 900’ / 8” sewer line bore for new construction site on budget and on time.

Client: Stan Miller

Time-line: 16 days

Equipment Used: JT100 Ditch Witch directional drill

Distance: 900’

Location: Breckenridge, CO

Client Issue: Client needed a sewer line for new construction in mountain area.

Americom Solution: Americom used it’s large JT100 directional drill to bore in at a 1% grade with 8” pipe […]

IHP 4”, 8” Gas and 12” Casing Park City, UT

2017-10-24T10:10:27+00:00

Scope of work: Horizontal Directional Drilled Approximately 1000’ of 12” Casing in rock. Horizontal Directional Drilled Approximately 400’ of 8” gas line and 2000’ of 4”.

  • Client: Flare Construction Inc.
  • Time-line: September, 2017 – October, 2017
  • Equipment Used: DitchWitch MT16
  • Distance: 1400 feet
  • Location: Park City, UT
  • Client Issue: Client needed to replace existing gas […]