PROJECT: Tallgrass Iron Horse pipeline

2019-03-26T13:18:12+00:00

 

PROJECT: Tallgrass Iron Horse pipeline

CUSTOMER: Jomax Pipeline Construction

LOCATION: I-25 Douglas, Wyoming

PROJECT INFO: Americom Technology inc. was contracted through Jomax Pipeline Construction to complete work on the Iron Horse pipeline project installing over 9,000 ft of 16” gas pipe and 1.25” communications pipe. (Including drill shots of 2500’ and 3,500’ in length.)

Meritage Midstream pipeline

2019-03-26T13:17:48+00:00

Customer: Jomax Construction

Location: Douglas, Wyoming

Project Specifications: Americom Technology inc. was contracted through Jomax Pipeline Construction on the Midstream pipeline project with Meritage Midstream to install over 4,000 ft of 20” gas pipeline.  Americom is currently running (2) 100,000 lb drills to complete the ongoing project.

 

Power conduit and utility box installation, Herriman, UT

2018-12-14T15:30:57+00:00

Client: Rocky Mountain Power

General Contractor: Sturgeon Electric

Location: Herriman, UT

Scope of work: Americom Technology performed trenching and directional drilling while placing 6,165 feet of (1) 6” underground power conduit and placed (8) 7X12 underground concrete utility boxes. This project included the teamwork of our Directional Drilling crews, excavation teams and our underground utility unit to complete […]

Wanship Fiber/Conduit installation

2018-12-14T15:26:48+00:00

Project: Wanship Fiber/Conduit installation

Customer: Beehive Telecom

Location: Wanship, UT

Americom utility crews installed 10,650 feet of (1) 2” conduit using both spider plow and directional drilling construction methods.  Americom then installed a 48-strand fiber optic cable through the new conduit structure connecting the new cable to communication towers.

Americom also excavated and set (5) 24”X36” utility vaults.

Jomax Construction 6” wireline – Greenley, CO

2018-06-19T15:23:32+00:00

Client: Jomax Construction

Time-line: 4 days

Equipment Used: 100 JT Ditch Witch directional drill

Distance: 950’

Location: Greenley, CO

Client Issue: Client needed to place a gas pipeline under a large construction project.

Americom Solution: Americom used it’s large 100 JT directional drill to meet the timeline, budget and expecation.